Description:

Presenter: Christophe Bragard, Tunnel Manager, Regional Connector Contractors

Regional Connector Contractors, a Skanska/Traylor JV, just completed the excavation (SEM) and construction of a 58-ft. wide, 36-ft. tall, cavern in the heart of downtown Los Angeles. This case history presentation will discuss the constraints, challenges and technologies used for the successful completion of the works. 

Recorded Date: June 24, 2020
Speaker(s): Christophe Bragard
Format: MP4
Download Size: 131.92 MB
Length: 50:22
  • List Price: $10.00
Item Details:
Construction of an Underground Cavern in the Heart of Downtown in the 21st Century
Back to Construction of an Underground Cavern in the Heart of Downtown in the 21st Century

0

An error has occurred. An error has occurred.